Duration: December 2004-April 2006 Mohara water supply project

Description:

Mohara Water Supply Project consist the following major components:

– Construction of a 90 MLD Surface Water Treatment Plant with all necessary treatment units (except river water intake and raw water pump house) including electrical, mechanical and chemical facilities etc.
– Construction of transmission and distribution pipelines for transmission and distribution of water produced from the proposed expansion of Mohara Water Treatment Plant.
– Rehabilitation of the existing Patenga Booster Station with the objectives to meet the required water demand in the Patenga area.

Services:

– Preparation of preliminary design of the plant and specification for different works and process
– Design of transmission & distribution pipe line (300 mm and above dia)
– Preparation of tender document for appointment of contractor for design, construction and commissioning of Mohara Water Treatment Plant and rehabilitation of Patenga Booster station
– Preparation of tender document for appointment of contractor/supplier for supply and installation of transmission & distribution pipe line (300 mm and above dia)

Funding agency: Government of Bangladesh